Timeline for Pharmacy Carve–in Transition/Communication Plan
July 5, 2011
Action | Responsible Party | Target Date | Status | |
---|---|---|---|---|
Transition Plan draft finalized | DOH | 4/29/2011 | ✓ | |
Transition Plan guidance vetted and finalized with Trade Associations | DOH | 5/11/2011 | ✓ | |
Transition Plan guidance issued to and finalized with plans | DOH | 5/24/2011 | ✓ | |
Transition Plan requirements provided to plans | DOH | 5/31/2011 | ✓ | |
Full pharmacy data file provided to the plans | DOH | 6/10 to 6/18/2011 | ✓ | |
Plans provided with PMPM | DOH | 7/8/2011 | ✓ | |
Transition Plan and formulary submitted to DOH | MCOs | 7/25/2011 ( or 44 days after receipt of full pharmacy file) | ✓ | |
Claims Data, Special Populations, and Supply Analysis/Action Plan submitted to DOH | MCOs | 7/25/2011 (or 44 days after receipt of full pharmacy file) | ✓ | |
Special Edition Medicaid Update and monthly Medicaid Update | DOH | 7/28/2011 | ✓ | |
DOH notification to plans of members restricted to pharmacy/provider | DOH | 8/1/2011 | ◉ | |
Plan/PBM Call Center available for general questions | MCOs | 8/2011 | ◉ | |
Updated 8/25/11 DOH notification to recipients |
DOH | ✓ | ||
DOH email blast to providers | DOH | 8/15/2011 (continuing weekly) | ✓ | |
Updated 8/17/11 DOH review/approval of MCO Transition Plans |
DOH | 8/17/2011 | ✓ | |
Medicaid Update and Poster | DOH | 8/31/2011 | ◉ | |
Plan notifications to providers | MCOs | On or after 8/22/2011 | ◉ | |
Updated 8/12/11 Plan notifications to recipients (also may include targeted mailings, if needed) |
MCOs | 8/31/2011 – 9/7/2011 |
◉ | |
Updated 8/12/11 Plan/PBM call center available for specific questions. |
MCOs | ◉ | ||
Web site Updates | MCOs | 8/15/2011 – 10/1/2011 | ◉ | |
Transition Plan /Formulary amendments submitted to DOH | MCOs | 8/22/2011 | ✓ | |
Provider Outreach Conducted | MCOs | 8/22/2011 – 10/1/2011 | ◉ | |
Medicaid Update | DOH | 9/2011 | ◉ | |
Follow up targeted mailings (If needed) | MCOs | 9/8/2011 – 9/15/2011 | ◉ | |
"Catch Up" data file provided to plans | DOH | 9/1/2011 | ◉ | |
Implementation | MCOs | 10/1/2011 | ◉ | |
Post Implementation monitoring and follow up | MCOs | Daily upon implementation will modify frequency as needed. | ◉ |