Tentative MRT Waiver/DSRIP Key Dates Year 2*
| 2016 | |
|---|---|
| April 1 | DSRIP Year 2 begins |
| April 7 | Final PPS Year 1 Third Quarterly Reports posted to DSRIP Website |
| April 18 | Public Comment period for Value Based Payment Roadmap closes |
| April 30 | PPS Year 1 Fourth Quarterly Reports (1/1/16 – 3/31/16) due from PPS |
| May 3 | PPS Regional Learning Symposium (Downstate) |
| May 4 | 1115 Waiver Public Comment Day (Downstate) |
| May 17 | PPS Regional Learning Symposium (Upstate) |
| May 31 | Independent Assessor provides feedback to PPS on PPS Year 1 Fourth Quarterly Reports; 15–day Remediation window begins |
| June 14 | Revised PPS Year 1 Fourth Quarterly Reports due from PPS; 15–day Remediation window closes |
| June 30 | Final Approval of PPS Year 1 Fourth Quarterly Reports |
| July 6 | Final PPS Year 1 Fourth Quarterly Reports posted to DSRIP Website |
| July 12 | 1115 Waiver Public Comment Day (Upstate) |
| August 1 | Initiate Mid–Point Assessment for PPS |
| August 1 | PPS Lead Regulatory Waiver Requests – Round 3 due |
| August 3 | DY1 Third DSRIP Payment to PPS |
| August 5 | PPS Year 2 First Quarterly Reports (4/1/16 – 6/30/16) due from PPS |
| August 8 to September 8 | Open PPS Performance Networks in MAPP for additions |
| August 31 | PPS submit Primary Care Project Narrative |
| September 4 | Independent Assessor provides feedback to PPS on PPS Year 2 First Quarterly Reports; 15–day Remediation window begins |
| September 19 | Revised PPS Year 2 First Quarterly Reports due from PPS; 15–day Remediation window closes |
| September 20–22 | 2nd Annual PPS Statewide Learning Symposium |
| September 30 | Final Approval of PPS Year 2 First Quarterly Reports |
| October | Round Two Regulatory Waiver responses completed |
| October | Implementation of Phase II Payment Scorecard in MAPP Performance Dashboards |
| October 6 | Final PPS Year 2 First Quarterly Reports posted to DSRIP Website |
| October 7 | DSRIP Project Approval & Oversight Panel convenes for briefing on Mid–Point Assessment process. |
| October 31 | PPS Year 2 Second Quarterly Reports (7/1/16 – 9/30/16) due from PPS |
| November 10 | Release PPS Primary Care Project Narratives for 30 day public comment period |
| November 22 | Release Initial Mid–Point Assessment recommendations to PPS for review |
| November 29 | Release Initial Mid–Point Assessment recommendations to public for comment |
| December 1 | Independent Assessor provides feedback to PPS on PPS Year 2 Second Quarterly Reports; 15–day Remediation window begins |
| December 15 | Revised PPS Year 2 Second Quarterly Reports due from PPS; 15–day Remediation window closes |
| December 21 | Public comment period for Initial Mid–Point Assessment recommendations and Primary Care Narratives ends |
| December 30 | Final Approval of PPS Year 2 Second Quarterly Reports |
| 2017 | |
| January 2017 | Anticipated Independent Evaluator contract start date |
| January 3 | Release Final Mid–Point Assessment recommendations for 30–day public comment |
| January 6 | Final PPS Year 2 Second Quarterly Reports posted to DSRIP Website |
| January 23 | Public Comment period for Final Mid–Point Assessment recommendations ends |
| January 31 | PPS Year 2 Third Quarterly Reports (10/1/16 – 12/31/16) due from PPS |
| January 31–February 3 | DSRIP Project Approval & Oversight Panel convenes to review Mid–Point Assessment recommendations |
| Late January | DY2 First DSRIP Payment to PPS |
| March 3 | Independent Assessor provides feedback to PPS on PPS Year 2 Third Quarterly Reports; 15–day Remediation window begins |
| March 10 | PPS complete Mid–Point Assessment Action Plans for Mid–Point Assessment Project Plan modifications and submit for IA review and approval |
| March 17 | Revised PPS Year 2 Third Quarterly Reports due from PPS; 15–day Remediation window closes |
| April 1 | Final Approval of PPS Year 2 Third Quarterly Reports |
| April 1 | DSRIP Year 3 begins |
* All dates are subject to change.