Value Based Payment Quality Improvement Program (VBP QIP) Timeline

  • Timeline is also available in Portable Document Format (PDF)

Last Edited: March 27, 2017

VBP QIP Timeline as of March 2017

Please note that the dates included herein are the Department of Health´s (DOH´s) recommended completion dates for past, present, and upcoming VBP QIP milestones. It is up to individual pairings of VBP QIP partners to determine the exact completion dates for each of the following items. To successfully participate in VBP QIP and to continue to receive payments, these milestones must be met and reported on in the proper order as detailed below, but the exact timing is left to the discretion of the Managed Care Organizations (MCOs), in coordination with its paired PPS and Facilities.

Note that dates in red must be completed by their listed times and cannot be pushed back.

Group 1 Timeline: Demonstration Year (DY) 1 – 2

The timeline for Group 1 is for participants, who began participating in VBP QIP in DY1.

Milestone Due Date Completed
Applications / Contracts
MCOs submit VBP QIP applications to DOH August 21, 2015
MCO VBP QIP applications approved by DOH September 11, 2015
MCOs, Performing Provider Systems (PPS), and Facilities put VBP QIP contract agreements in place 1 October 9, 2015
Rates / Payments
DOH finalizes rates and sends to Centers for Medicare and Medicaid Services (CMS)/ Division of Budget (DOB) for review September 18, 2015
DOH effectuates the State share payment to the MCOs October 14, 2015
MCOs to submit December 2015 interim report (for VIP QIP payment disbursements made during the month of October 2015 – two month lag) December 4, 2015
January rate adjustments for DY1 approved by CMS TBD  
April 2016 rates approved by CMS/DOB November 2016
Governance Document
MCOs submit VBP QIP Governance Document 2 for DOH review March 7, 2016
DOH completes first round of review of MCO VBP QIP Governance Document and provides comments to the MCOs April 26, 2016
MCOs submit a revised VBP QIP Governance Document to DOH for review September 16, 2016
DOH reviews and approves VBP QIP MCO Governance Document October 11, 2016
Facility Plan
DOH to provide a Facility Plan 3 outline to the MCOs for review September 30, 2015
MCOs submit Facility Plans outline comments to DOH October 9, 2015
DOH to finalize Facility Plan template guidance with the MCOs, ensuring consistency with VBP Roadmap October 23, 2015
MCOs develop and issue Facility Plan templates February 18, 2016
MCOs to issue the Facility Plan template to the PPS for comments February 18, 2016
Facilities submit draft Facility Plan to PPS for initial review May 2, 2016
PPS review Facility Plan and return them to facilities for revision May 27, 2016
Facilities complete Facility Plans and submit to PPS, MCO, and DOH for review June 20, 2016
Facility Plans reviewed by MCO in collaboration with PPS (final copies should be sent to DOH) September 16, 2016
DOH to distribute Facility Plan Guidance Packet to VBP QIP partners January 27, 2017
DOH to release VBP QIP DY3 Guidance Document March 17, 2017
Facilities submit their updated, MCO approved, final Facility Plan to DOH March 31, 2017  
Metrics / Benchmarks
Baseline metrics for future measurement are co–developed by facility, PPS, & MCO (submitted as part of the final Facility Plan) March 31, 2017  
Benchmarks for reporting & performance set to be revisited quarterly Ongoing: Quarterly Starting October 1, 2017  
Reporting
MCO Monthly Reporting to DOH (January to March 2016), for disbursements made October to January 2016 – Manual Submissions 4 4th of the Month
MCO Quarterly Reporting to DOH (April 2016 – Ongoing) – MMCOR Submissions Ongoing: 45 days after Quarter End 5  

Group 2 Timeline: DY2

The timeline for Group 2 is for participants who began participating in VBP QIP in DY2.

Milestone Due Date Completed
Applications / Contracts
MCOs submit VBP QIP applications to DOH June 13, 2016
MCO VBP QIP applications approved by DOH June 17, 2016
MCOs, PPS, and Facilities put VBP QIP contract agreements in place September 30, 2016
Rates / Payments
April 2016 rates approved by CMS/DOB November 2016
DOH effectuates the State share payment to the MCOs July/August 2016
Governance Document
MCOs submit VBP QIP Governance Document for DOH review October 7, 2016
DOH completes first round of review of MCO VBP QIP Governance Document and provides comments to the MCOs October 21, 2016
MCOs submit a revised VBP QIP Governance Document to DOH for review December 9, 2016
DOH reviews VBP QIP MCO Governance Document February 24, 2017
MCOs submit a revised VBP QIP Governance Document to DOH for review (Group 2) March 24, 2017  
DOH reviews revised VBP QIP Governance Documents and sends updated scorecards to MCOs March 31, 2017  
Facility Plan
DOH to provide a Facility Plan outline to the MCOs for review July 10, 2016
DOH to send Facility Plan template guidance with the MCOs, ensuring consistency with VBP Roadmap July 10, 2016
MCOs develop and issue Facility Plan templates September 9, 2016
MCOs to issue the Facility Plan template to the PPSs for comments September 9, 2016
Facilities submit draft Facility Plan to PPS for initial review October 14, 2016
PPSs review Facility Plan and return them to facilities for revision October 28, 2016
Facilities complete Facility Plan and submit to PPS, MCO, and DOH for review November 11, 2016
Facility Plans reviewed by MCO in collaboration with PPS (final copies should be sent to DOH) December 9, 2016
DOH to distribute Facility Plan Guidance Packet to VBP QIP partners January 27, 2017
DOH to release VBP QIP DY3 Guidance Document March 17, 2017
Facilities to submit updated, MCO approved, final Facility Plan to DOH March 31, 2017  
Metrics / Benchmarks
Baseline metrics for future measurement are co–developed by facility, PPS, & MCO (submitted as part of the Facility Plan) March 31, 2017  
Benchmarks for reporting & performance set to be revisited quarterly Ongoing: Quarterly Starting October 1, 2017  
Reporting
MCO Quarterly Reporting to DOH (April 2016 – Ongoing) – MMCOR Submissions Ongoing: 45 days after Quarter End 5  

Group 1 and Group 2: DY3 to DY5 Timeline

Beginning in DY3, both groups will have the same timeline. This section will be populated once milestones are established for DYs 3 to 5.

Milestone Due Date Completed
Governance Document
MCOs to make updates to the Governance Plans as appropriate (copies must be sent to DOH) Ongoing  
Facility Plan
MCOs to make updates to the Facility Plans as appropriate (copies must be sent to DOH) Ongoing  
Pay for Reporting (P4R): VBP Contracting
Facilities must provide paired MCO and DOH with a Letter of Intent (LOI) for at least one VBP contract by July 1, 2017 (LOI may be substituted with a Contract Attestation if a VBP contract already exists by April 1, 2017) April 1, 2017  
Facilities must provide DOH (only) with the MCO Contract List of current Medicaid Managed Care Contracts including 2015 cost data for each Medicaid Managed Care contract the facility has and should also include projections for which VBP contracts will have a Total Care for General Population (TCGP) value–based arrangement by April 1, 2018 April 1, 2017  
Facilities must provide paired MCO and DOH with at least one Contract Attestation confirming parties intend to sign a VBP contract in accordance with the NYS Roadmap July 1, 2017  
Facilities must provide paired MCO and DOH with LOIs with the remaining Medicaid MCOs for VBP contracts by April 1, 2018 (LOI may be substituted with Contract Attestations if a VBP contract already exist by July 1, 2017) July 1, 2017  
Facilities must provide DOH (only) with the updated MCO Contract List of current Medicaid Managed Care Contracts including 2016 cost data for each Medicaid Managed Care contract the facility has and should also include projections for which VBP contracts will have a TCGP value–based arrangement by April 1, 2018 July 1, 2017  
Facilities must provide paired MCO and DOH with a signed Facility Attestation related to 2016 cost data reported in the Medicaid MCO list July 1, 2017  
Facilities continue to execute contracts to meet deadline by April 1, 2018 July 1, 2017 to March 31, 2018  
Facility must provide DOH and their VBP QIP paired MCO Contract Attestations confirming that the partners have indeed signed VBP contracts and that these contracts fulfill the requirements of the NYS VBP Roadmap. The VBP QIP paired MCO will check contract attestations against LOIs submitted in July 2017 Note: The VBP QIP facility must have Medicaid MCO contracts where at least 80% of total Medicaid MCO contracted payments (based on the 2016 data reported in the July 1, 2017 MCO Contract List) to the facility are tied to at least Level 1 value–based purchasing components April 1, 2017  
Pay for Performance (P4P): VBP QIP Quality Measurement
DOH to release the statewide mean for measures for DY4 for AIT measurement June 2017  
DOH to release the statewide mean for measures for DY5 for AIT measurement June 2018  
Facilities to submit P4P measures to their paired MCOs Quarterly: Beginning DY3 Q3, no later than 120 days after close of Quarter  
MCOs to review and approve reports Quarterly: Beginning DY3 Q3, no later than 45 days after initial submission  
MCOs to notify facilities of decision prepare monthly payments Quarterly: Beginning DY3 Q3, no later than 180 days after close of Quarter  
Reporting
MCO Quarterly Reporting to DOH (April 2016 – Ongoing) – MMCOR Submissions Ongoing: 45 days after Quarter End  
Facilities report on selected measures on quarterly basis Ongoing: Quarterly  

Group 1 and Group 2: Timeline Diagram

Group 2 will complete the first two years of VBP QIP deliverables within one year, using the templates, guidelines, and lessons learned from Group 1 to meet their accelerated milestones

timeline diagram

_______________________________________________________

1. It is expected that the agreements will be put in place to extend through 2020, knowing that these agreements will be amended over time as the program matures. 1
2. MCO Governance Document refers to the documents submit by MCOs that establish governance for VBP QIP. 2
3. Facility Plans should reflect a distressed facility´s overall approach to improve quality and outcomes in a way that aligns with NYS´ Payment Reform as a means to achieve long–term sustainability. 3
4. Beginning in Q2 of SFY2016–17, monthly reporting should be submitted through the Medicaid Managed Care Operating Report (MMCOR). 4
5. Visit the DOH website to view DSRIP Timelines for reporting due dates. 5